Olympic Dam smelter shutdown camp — 2 × Basecamp 32
Q-26-0118 · BHP Olympic Dam · Hire · Basecamp 32 · Sent
Humanihut Pty Ltd — Field Infrastructure Systems
290 Glen Osmond Road, Fullarton SA 5063 · Factory: Tonsley SA
+61 436 965 586 · sales@humanihut.com · humanihut.com
ABN 71 163 752 994 · ISO 9001 · ISO 14001 · ISO 45001
290 Glen Osmond Road, Fullarton SA 5063 · Factory: Tonsley SA
+61 436 965 586 · sales@humanihut.com · humanihut.com
ABN 71 163 752 994 · ISO 9001 · ISO 14001 · ISO 45001
Quotation
Q-26-0118
02 Oct 2026
Valid until 30 Oct 2026
Proposed start 16 Nov 2026
Prepared for
BHP Olympic Dam
Craig Whittaker, Shutdown Manager — Smelter
Olympic Dam Operations, Andamooka Road, Roxby Downs SA
ABN 49 004 028 077
Olympic Dam Operations, Andamooka Road, Roxby Downs SA
ABN 49 004 028 077
Scope
Hire of a Basecamp 32 at Olympic Dam village overflow site, SA for 12 weeks — accommodation for up to 512 personnel.
| Description | Qty | Unit | Amount | |
|---|---|---|---|---|
| 6m Hut — hire, 12 weeks | 64 | $6,240.00 | $399,360.00 | |
| Bathroom module — hire, 12 weeks | 12 | $15,000.00 | $180,000.00 | |
| Kitchen module — hire, 12 weeks | 1 | $31,200.00 | $31,200.00 | |
| Laundry module — hire, 12 weeks | 1 | $14,400.00 | $14,400.00 | |
| Power module 125 kVA — hire, 12 weeks | 2 | $13,200.00 | $26,400.00 | |
| Potable water module 18,000 L — hire, 12 weeks | 1 | $5,400.00 | $5,400.00 | |
| Wastewater module 36,000 L — hire, 12 weeks | 1 | $7,440.00 | $7,440.00 | |
| Covered dining & recreation area — hire, 12 weeks | 4 | $3,120.00 | $12,480.00 | |
| Mobilisation and transport to site | 1 | $148,000.00 | $148,000.00 | |
| Installation and utilities connection | 1 | $96,000.00 | $96,000.00 | |
| Site management — 24/7 onsite manager, cleaning, linen and consumables (per week) | 12 | $18,500.00 | $222,000.00 | |
| Demobilisation, return freight and refurbishment | 1 | $88,000.00 | $88,000.00 | |
| Subtotal ex GST | $1,230,680.00 | |||
| GST 10% | $123,068.00 | |||
| Total incl GST | $1,353,748.00 | |||
Terms
Hire is charged monthly in arrears from the date the camp is handed over. Mobilisation and installation are invoiced on handover; demobilisation on completion. Units remain the property of Humanihut Pty Ltd. Payment terms 30 days EOM.
Smelter campaign shutdown SCM26. Craig needs beds on the ground by 30 Nov for 480 contractors at peak. Village services (catering) by BHP's existing provider; we supply site management, cleaning and linen.
Stephen Dubrich · Chief Operating Officer · Humanihut
Internal — not on the quote
- Value
- $1,230,680
- Cost
- $609,124
- Margin
- 50.5% $621,556
- Owner
- Stephen Dubrich
- Status
- Sent
Fleet available today
Hire fleet in the yard, unallocated
6m Hut32 free / 64 needed 32 short
Bathroom module5 free / 12 needed 7 short
Kitchen module1 free / 1 needed OK
Laundry module0 free / 1 needed 1 short
Power module 125 kVA3 free / 2 needed OK
Potable water module 18,000 L3 free / 1 needed OK
Wastewater module 36,000 L3 free / 1 needed OK
Covered dining & recreation area6 free / 4 needed OK
Winning the quote opens the project and runs the plan: free units are allocated and the shortfall goes to work orders at Tonsley.