Cleaning chemical kit — site

HH-C-CL01 · Site consumables · Bunzl Australasia · bin S-05

On hand
58 kit
$3,712.00
Reserved
0
0 planned work orders
Available
58
OK · min 30
On order
0
reorder qty 40 · 4 days lead
Ledger
Every receipt, issue, return and count — the balance column ends at what's on the shelf
WhenMovementRefNoteQtyBalance
12 Oct, 8:25am Issue to site HP-26-033 Top-up — Moomba gas plant -3 58
12 Oct, 8:25am Issue to site HP-26-029 Top-up — Ceduna Hospital campus -1 61
11 Oct, 8:15am Issue to site HP-26-036 Opening kit — Port Lincoln terminal -5 62
10 Oct, 8:20am Issue to site HP-26-037 Top-up — Fitzroy Crossing -3 67
10 Oct, 8:20am Issue to site HP-26-029 Top-up — Ceduna Hospital campus -4 70
7 Oct, 8:15am Issue to site HP-26-046 Opening kit — Murray Bridge training ground -2 74
6 Oct, 8:20am Issue to site HP-26-041 Top-up — Parndana, Kangaroo Island -9 76
3 Oct, 8:20am Issue to site HP-26-033 Top-up — Moomba gas plant -1 85
1 Oct, 10:40am Receipt PO-26-0318 Received from Bunzl Australasia +40 86
26 Sep, 8:20am Issue to site HP-26-037 Top-up — Fitzroy Crossing -7 46
26 Sep, 8:20am Issue to site HP-26-029 Top-up — Ceduna Hospital campus -4 53
22 Sep, 8:15am Issue to site HP-26-041 Opening kit — Parndana, Kangaroo Island -19 57
19 Sep, 8:20am Issue to site HP-26-033 Top-up — Moomba gas plant -1 76
12 Sep, 8:20am Issue to site HP-26-037 Top-up — Fitzroy Crossing -7 77
12 Sep, 8:20am Issue to site HP-26-029 Top-up — Ceduna Hospital campus -4 84
5 Sep, 8:20am Issue to site HP-26-033 Top-up — Moomba gas plant -1 88
29 Aug, 8:20am Issue to site HP-26-037 Top-up — Fitzroy Crossing -7 89
29 Aug, 8:20am Issue to site HP-26-029 Top-up — Ceduna Hospital campus -4 96
27 Aug, 10:40am Receipt PO-26-0312 Received from Bunzl Australasia +40 100
22 Aug, 8:20am Issue to site HP-26-033 Top-up — Moomba gas plant -1 60
15 Aug, 8:20am Issue to site HP-26-037 Top-up — Fitzroy Crossing -7 61
15 Aug, 8:20am Issue to site HP-26-029 Top-up — Ceduna Hospital campus -4 68
8 Aug, 8:15am Issue to site HP-26-033 Opening kit — Moomba gas plant -2 72
1 Aug, 8:20am Issue to site HP-26-037 Top-up — Fitzroy Crossing -7 74
1 Aug, 8:20am Issue to site HP-26-029 Top-up — Ceduna Hospital campus -4 81
18 Jul, 8:20am Issue to site HP-26-037 Top-up — Fitzroy Crossing -7 85
18 Jul, 8:20am Issue to site HP-26-029 Top-up — Ceduna Hospital campus -4 92
12 Jul, 10:40am Receipt PO-26-0305 Received from Bunzl Australasia +40 96
4 Jul, 8:20am Issue to site HP-26-037 Top-up — Fitzroy Crossing -7 56
4 Jul, 8:15am Issue to site HP-26-029 Opening kit — Ceduna Hospital campus -6 63
1 Jul, 7:00am Stocktake ST-26-07 Opening stocktake — 1 Jul 2026 +143 69
20 Jun, 8:20am Issue to site HP-26-037 Top-up — Fitzroy Crossing -7 -74
6 Jun, 8:20am Issue to site HP-26-037 Top-up — Fitzroy Crossing -7 -67
23 May, 8:20am Issue to site HP-26-037 Top-up — Fitzroy Crossing -7 -60
9 May, 8:20am Issue to site HP-26-037 Top-up — Fitzroy Crossing -7 -53
25 Apr, 8:20am Issue to site HP-26-037 Top-up — Fitzroy Crossing -7 -46
11 Apr, 8:20am Issue to site HP-26-037 Top-up — Fitzroy Crossing -7 -39
28 Mar, 8:20am Issue to site HP-26-037 Top-up — Fitzroy Crossing -7 -32
14 Mar, 8:20am Issue to site HP-26-037 Top-up — Fitzroy Crossing -7 -25
28 Feb, 8:20am Issue to site HP-26-037 Top-up — Fitzroy Crossing -7 -18
14 Feb, 8:15am Issue to site HP-26-037 Opening kit — Fitzroy Crossing -11 -11
Purchase orders
PO-26-0318Received40/40
PO-26-0312Received40/40
PO-26-0305Received40/40
Out at sites