Projects / HP-26-041
NEMS Camp 2 activation — Kangaroo Island bushfire recovery
HP-26-041 · National Emergency Management Agency · NEMS activation · NEMS emergency shelter camp · Parndana, Kangaroo Island, SA
Contract value
$886k
At risk · Rhys Nolan
Invoiced
$233k
$255,750 owing incl GST
Cost to date
$168k
budget $666k
Forecast margin
25%
$220,080
Units
43/43
all allocated
Open tasks
4
none overdue
Requirements and allocation
What the site needs, what's allocated from the NEMS stockpile, and what's being built
| Product | Needed | Allocated | In build | To source | |
|---|---|---|---|---|---|
| 6m HutMade at Tonsley | 29 | 29 | — | 0 | |
| Bathroom moduleMade at Tonsley | 6 | 6 | — | 0 | |
| Accessible bathroom module | 1 | 1 | — | 0 | |
| Power module 125 kVA | 1 | 1 | — | 0 | |
| Potable water module 18,000 L | 1 | 1 | — | 0 | |
| Wastewater module 36,000 L | 1 | 1 | — | 0 | |
| Covered dining & recreation area | 4 | 4 | — | 0 |
Allocated units
43 serials · 16 containers — straight from the fleet register
Bathroom module · 6
6m Hut · 29
HH6-23-0030HH6-23-0031HH6-23-0032HH6-23-0033HH6-23-0034HH6-23-0035HH6-23-0036HH6-23-0037HH6-23-0038HH6-23-0039HH6-23-0040HH6-23-0041HH6-23-0042HH6-23-0043HH6-23-0044HH6-23-0045HH6-23-0046HH6-23-0047HH6-23-0048HH6-23-0049HH6-23-0050HH6-23-0051HH6-23-0052HH6-23-0053HH6-23-0054HH6-23-0055HH6-23-0056HH6-23-0057HH6-23-0058
Power module 125 kVA · 1
Potable water module 18,000 L · 1
Wastewater module 36,000 L · 1
Covered dining & recreation area · 4
Accessible bathroom module · 1
Allocated In transit Deployed
Manufacturing and purchasing
Work orders building for this project, and the purchase orders raised for it
| Ref | What | Status | Dates | Value |
|---|---|---|---|---|
| PO-26-0322 | Healthcare Linen SA | Sent | raised 12 Oct · due 16 Oct | $10,520 |
Tasks
4 open
| Confirm Tuesday ferry slot for consumables top-up SeaLink holding 2 × 12 m slots — confirm by 3pm. | Mia Tran | 16 Oct | In progressHigh | ||
| Weekly site report to NEMA | Rhys Nolan | 16 Oct | To do | ||
| Generator service — 250 h | Kurt Bauer | 19 Oct | To do | ||
| Rotate onsite manager (Kurt → relief) | Rhys Nolan | 23 Oct | To do | ||
| Ground survey and levelling — Parndana oval | Kurt Bauer | 18 Sep | Done | ||
| Site induction pack — KI Council | Rhys Nolan | 22 Sep | Done |
Site consumables
On site at Parndana, Kangaroo Island, used per day and days of cover — sent from the depot, counted on site
| Item | On site | Per day | Cover | To target | At depot | Counted | |
|---|---|---|---|---|---|---|---|
| Toilet paper — carton of 48 | 9 ctn | 2.8 | 3.2 days | 31 | 62 | 11 Oct | |
| Linen pack — single bed (2 sheets, pillowcase) | 149 ea | 33.2 | 4.5 days | 316 | 640 | 14 Oct | |
| Hand soap 5 L | 5 ea | 1.0 | 5.0 days | 16 | 96 | 12 Oct | |
| Cleaning chemical kit — site | 9 kit | 0.9 | 10.0 days | 10 | 58 | 14 Oct | |
| Bath towel | 365 ea | 33.2 | 11 days | 100 | 560 | 9 Oct | |
| Water treatment tablets — tub of 200 | 4 tub | 0.3 | 13.3 days | 5 | 24 | 10 Oct | |
| First-aid restock kit | 3 kit | 0.2 | 15.0 days | 3 | 26 | 13 Oct | |
| Bin liners — carton of 250 | 13 ctn | 0.8 | 16 days | 4 | 70 | 13 Oct | |
| Mattress protector — single | 54 ea | 3.2 | 17 days | 14 | 260 | 11 Oct | |
| PPE kit — site crew | 6 kit | 0.3 | 20 days | 3 | 44 | 11 Oct |
Costs
$133,920.00 booked · consumables $34,225.60 · fleet charge in budget
| 23 Sep 2026 | Crane hire | Franna and 60 t crane — offload and placement Boom Logistics | $29,760.00 | |
| 19 Sep 2026 | Freight | SeaLink ferry crossings — Cape Jervis → Penneshaw SeaLink | $40,920.00 | |
| 18 Sep 2026 | Freight | Road freight Adelaide → Cape Jervis, 9 × Hi-Cube Toll Transport | $63,240.00 |
Invoices
$232,500.00 ex GST invoiced · $0.00 received
- Customer
- National Emergency Management Agency
- Contact
- Kirsten MahonyDirector, National Emergency Stockpile
- Kind
- NEMS activation
- Configuration
- NEMS emergency shelter camp
- Site
- Parndana, Kangaroo Island, SA
- Personnel
- 232
- Project manager
- Rhys Nolan
- Start
- 14 Sep 2026
- On site
- 24 Sep 2026
- Until
- 18 Dec 2026
- Customer PO
- NEMA-ACT-26-07
- Planned
- 31 Aug 2026
Ferry crossings (SeaLink, Cape Jervis → Penneshaw) book out on weekends — consumables top-ups go Tuesday and Thursday.
On the schedule
Schedule HP-26-041 Consumables run — ferry 20 Oct · 1d
Timeline
14 Sep, 8:10am · Rhys Nolan