Projects / HP-26-046
SES volunteer training camp — Murray Bridge
HP-26-046 · SA State Emergency Service · Hire · The Cooper · Murray Bridge training ground, SA
Contract value
$16k
On track · Sam Kowalski
Invoiced
$7k
$7,920 owing incl GST
Cost to date
$6k
budget $9k
Forecast margin
40%
$6,206
Units
4/4
all allocated
Open tasks
1
none overdue
Requirements and allocation
What the site needs, what's allocated from the hire fleet, and what's being built
| Product | Needed | Allocated | In build | To source | |
|---|---|---|---|---|---|
| 6m HutMade at Tonsley | 3 | 3 | — | 0 | |
| Cooper life-support pack | 1 | 1 | — | 0 |
Allocated units
4 serials · 2 containers — straight from the fleet register
6m Hut · 3
Cooper life-support pack · 1
Allocated In transit Deployed
Tasks
1 open
| Pick-up and return — Murray Bridge | Sam Kowalski | 23 Oct | To do |
Site consumables
On site at Murray Bridge training ground, used per day and days of cover — sent from the depot, counted on site
| Item | On site | Per day | Cover | To target | At depot | Counted | |
|---|---|---|---|---|---|---|---|
| Toilet paper — carton of 48 | 1 ctn | 0.1 | 10 days | 1 | 62 | 14 Oct | |
| Cleaning chemical kit — site | 1 kit | 0.1 | 10.0 days | 2 | 58 | 10 Oct | |
| Water treatment tablets — tub of 200 | 1 tub | 0.1 | 10.0 days | 2 | 24 | 11 Oct | |
| PPE kit — site crew | 1 kit | 0.1 | 10.0 days | 2 | 44 | 14 Oct | |
| Mattress protector — single | 3 ea | 0.2 | 15 days | 2 | 260 | 11 Oct | |
| Linen pack — single bed (2 sheets, pillowcase) | 27 ea | 1.7 | 16 days | — | 640 | 9 Oct | |
| Bath towel | 31 ea | 1.7 | 18 days | — | 560 | 13 Oct | |
| Hand soap 5 L | 2 ea | 0.1 | 20 days | 1 | 96 | 14 Oct | |
| Bin liners — carton of 250 | 2 ctn | 0.1 | 20 days | 1 | 70 | 11 Oct | |
| First-aid restock kit | 2 kit | 0.1 | 20 days | 1 | 26 | 14 Oct |
Costs
$4,488.00 booked · consumables $1,942.30 · fleet charge in budget
| 12 Oct 2026 | Install crew | Install crew — labour and travel Humanihut crew | $1,320.00 | |
| 08 Oct 2026 | Crane hire | Franna and 60 t crane — offload and placement Freo Group | $768.00 | |
| 03 Oct 2026 | Freight | Road freight to Murray Bridge training ground Toll Transport | $2,400.00 |
Invoices
$7,200.00 ex GST invoiced · $0.00 received
| INV-20560 | Mobilisation | 09 Oct 2026 | $7,200.00 | Awaiting payment |
- Customer
- SA State Emergency Service
- Contact
- Tom HellyerState Training Officer
- Kind
- Hire
- Configuration
- The Cooper
- Site
- Murray Bridge training ground, SA
- Personnel
- 12
- Project manager
- Sam Kowalski
- Start
- 07 Oct 2026
- On site
- 09 Oct 2026
- Until
- 23 Oct 2026
- Customer PO
- SES-PO-26118
- Quote
- Q-26-0114
- Planned
- 23 Sep 2026
On the schedule
Schedule HP-26-046 Pick-up — Murray Bridge 23 Oct · 1d
Timeline
Nothing yet.