Schedule Demo 12 live projects · 6 open work orders
Accounts · synced 9:14am Thu 15 Oct 2026

Schedule

The Tonsley production line, transport and the install crews on one timeline. Drag a bar to move it, or onto another row; drag its right edge to change its length.

Open bookings
25
6 work orders · 12 projects
Huts through QA, next 4 wks
25
from QA & pack bookings
Installs in next 4 weeks
4
crews A and B
Clashes
1
double-booked resources
Busiest resource
Fit-out bay
16 of the next 20 working days booked
Clashes
Drag one of the bars so they no longer share a day — the clash clears on its own.
Install crew A HP-26-037 Demobilise and pack · WA Department of Communities overlaps HP-26-044 Install — Camp 5 · National Emergency Management Agency 21 Oct – 23 Oct
Resource
Panel line 1 at a time
Fold & frame bay 1 at a time
Fit-out bay 1 at a time
QA & pack 1 at a time
Transport & logistics
Install crew A 1 at a time
Install crew B 1 at a time
Site services
Thu 13 AugMon 17 AugMon 24 AugMon 31 AugMon 7 SepMon 14 SepMon 21 SepMon 28 SepMon 5 OctMon 12 Oct
1314171819202124252627283112347891011141516171821222324252829301256789121314
WO-26-0130 · Panel fabrication
WO-26-0131 · Panel fabrication
WO-26-0135 · Panel fabrication
WO-26-0133 · Panel fabrication
WO-26-0132 · Panel fabrication
WO-26-0134 · Panel fabrication
WO-26-0130 · Frame & fold assembly
WO-26-0131 · Frame & fold assembly
WO-26-0135 · Frame & fold assembly
WO-26-0133 · Frame & fold assembly
WO-26-0132 · Frame & fold assembly
WO-26-0130 · Fit-out & electrical
WO-26-0131 · Fit-out & electrical
WO-26-0135 · Fit-out & electrical
WO-26-0133 · Fit-out & electrical
WO-26-0132 · Fit-out & electrical
WO-26-0130 · QA & pack
WO-26-0131 · QA & pack
WO-26-0135 · QA & pack
WO-26-0133 · QA & pack
HP-26-044 · Road freight to Carnarvon
HP-26-034 · Install — Eneabba
HP-26-036 · Install — Port Lincoln
On trackAt riskLateOn hold Clash Left edge = project health · click a bar to edit